Scope of main works
In July 2010, the Shipowner JIF MAR did contract ATLANTIC REFIT CENTER and POLYCONTACT for the replacement of the entire transom of the ship. The works consists of removing the old transom (W 11 m x L 5 m, weight 4 T) and to reinstall the new prefabricated composite transom. Then, the new 16 Tons lift crane has been fitted on this new transom. The works have been performed in 3 weeks only at the entire satisfaction of the Captain and the Owner.